Scope Markup
Mark up the scope by package - feeds the scope and variation registers
Packages
10
in the scope
In-scope value
£1.41m
5 packages
Provisional
£48k
1 package
Variations
£49.7k
2 VOs
Scope register
Marked up against the contract and pricing schedule
| Ref | Package | Discipline | Value | Scope | Note |
|---|---|---|---|---|---|
| SC-001 | Demolition & strip-out | Struct | £86,000 | In scope | Per contract |
| SC-002 | Structural steel frame | Struct | £412,000 | In scope | Per contract |
| SC-003 | Curtain wall & glazing | Arch | £298,000 | In scope | Per contract |
| SC-004 | Mechanical services | MEP | £356,000 | In scope | Per contract |
| SC-005 | Electrical services | MEP | £241,000 | In scope | Per contract |
| SC-006 | Landscape & external works | Arch | £64,000 | Excluded | By others |
| SC-007 | FF&E | Arch | £120,000 | Excluded | Client direct |
| SC-008 | PV array (roof) | MEP | £48,000 | Provisional | Subject to feasibility |
| SC-009 | Reception feature joinery | Joinery | £31,500 | Variation | VO-012, instructed |
| SC-010 | Additional riser, level 3 | MEP | £18,200 | Variation | VO-014, pending |